PART OF THE CHRIST OUR LIGHT FAMILY OF PARISHES
SERVED BY THE MISSIONARIES OF THE PRECIOUS BLOOD
48 North Hanover Street, P.O. Box 93, Minster OH 45865 | 419-628-2614
The overall structure will remain the same, but the color will vary as copper naturally changes with age.
Initially, it will have a dark bronze hue, gradually changing to green over time.
We expect taking outdoor photos to be a challenge since scaffolding will be blocking some of the building from the late summer of 2025 and could continue into the summer of 2026.
The front steps of the church, the north handicap ramp and concrete steps all need to be replaced.
Additionally, a protective security system for the church will be installed and the rectory roof requires replacement.
The parish might need to borrow the money, attempt another fundraiser, or put off other
capital projects.
As in the past, if we collect more than we need for this project, the funds could be used for the gold crosses or will be transferred for use on the other significant St. Augustine projects.
Wellman Brothers out of Coldwater. They have worked on our steeples since the 1950’s and are one of the most respected in this field. The Archdiocese has approved them for the project.
Wellman Brothers recommends using copper exclusively because of its durability. Copper is also malleable, which allows for an accurate replication of the current steeple design. Furthermore, copper is easier to solder compared to other materials. The existing copper cannot be re-used as the material has degraded past the point of repair.
The value of the old copper is approximately $1 -$3 per pound (as of 01/2025). However, Wellman Brothers will retain the proceeds from the sale of the scrap copper to help offset the project's costs.
The project is expected to begin in the late summer of 2025 and is anticipated that it will be completed during the summer of 2026.
Until the project is started, the extent of wood damage behind the existing copper is
unknown. Depending on the leak damages, there could be a need to replace some structural wood components.
There will be a 3 year warranty, however the restoration should last many decades (perhaps 50 -75 years). The last major restoration was done in 1939.
We currently have a list of capital improvement projects that require funding of approximately $1.6 million. Additional projects have been identified but not yet quoted.
$250,000 has been allocated to the Steeple renovation project. This will allow enough money remaining to fund the additional capital projects previously identified.
In 1874, the twin towers were erected on the west side of the church by parishioner and master builder, Johann Anton Goehr. These towers replaced the original steeple which was on the east side of the church.
It is estimated that it has been over 40 years since the last major repairs or renovations were completed on the steeples.
The copper was replaced in 1939 and major reinforcements were done in 1964 after the steeples sustained severe wind damage.
190 feet, though the scaffolding to be used only reaches 125 feet. This is part of the reason that the crosses would be a separate project. All safety equipment will be supplied and used by Wellman Brothers.
Yes, during the reconstruction, improvements will be made to enhance the steeples’ durability. Currently, the area behind the copper consists only of air and structural beams. As part of the renovation, an ice shield will be added to better protect the steeples from the elements and ensure their longevity.
All Rights Reserved | St. Augustine | Site By: Midnet Media